iDemand Energy Storage begins 5-building solar+storage project in San Diego

$
0
0

Image from IDES3

iDemand Energy Storage (iDES3) has begun engineering and design work on a $4.1 million solar+storage project that will lower dependency on the investor-owned utility and reduce the carbon footprint for five buildings belonging to a San Diego County-based biotech company.

The contract to manufacture uninterrupted-energy-supply batteries capable of storing and discharging up to 1.078 MW of solar energy was awarded to iDES3 in early January by SunFusion Solar. Both are San Diego companies.

“One of the challenges of this project will be to customize solar awnings that will hang off the sides of the buildings,” said Ray Trejo, co-founder and senior vice president of six-month-old iDES3. “They will need to be specially engineered to ensure that they’re not too heavy. There will also be solar arrays atop carports and rooftops.”

Installation of the battery units and solar arrays is expected to be completed in mid-October. The name of the biotech company is being withheld pending iDES3’s patent applications for the solar storage technology, according to Trejo.

“This is the first of potentially several projects for the biotech company, which in addition to its buildings in San Diego County, also has facilities in Baja, Mexico,” said Sandy Ellard, president of SunFusion.

The client’s objective is to shave peak-load electricity demand during the middle of the day by using energy discharged from the battery units that was stored overnight. During peak-demand periods, utility companies charge higher rates than in off-peak times, Trejo said.

Rates may run as high as $20 per KW between noon and 6 p.m., and $15 per kilowatt from 6 p.m. to 10 p.m. “It all depends on the utility jurisdiction,” he said.

However, utility companies will essentially “double-dip” by adding what’s called a non-coincidental charge on top of the peak rate any time they detect a user’s maximum rate. “But our battery system looks for a rise in demand and it automatically discharges stored power to level off the demand load,” Trejo said.

The biotech contract, which calls for 900 kWh for the five-building load, is the largest to date for the startup battery manufacturer.

News item from IDES3